Customer |
Project Name |
Description |
|
1 |
Eskom Southern Region |
Keiskammahoek Electrification |
Electrification of 4500 erven |
|
2 |
Eskom Southern Region |
Libode Phase 1A & 1B Electrification |
MV and LV Reticulation of 3000 erven |
|
3 |
Eskom Southern Region |
Tsolo Developer Project |
Electrification of 439 stands |
|
4 |
Eskom Southern Region |
Qumbu Developer Project |
Electrification of 569 stands |
|
5 |
Eskom southern Region |
Peddie Wesley 22KV line |
Audit and Line Refurbishment |
|
6 |
Eskom Southern Region |
Schools |
Audit & Electrification of Schools in the Eastern
Cape |
|
7 |
Eskom Southern Region |
Kohlo Electrification |
Project Management of the Electrification of 4400
Connections |
|
8 |
Eskom Southern Region |
Zwallu Springfontein – 22KV Line Refurbishment |
Audit & Refurbishment of the 22KV line |
|
9 |
Eskom Southern Region |
Engcobo 5A & 5B Electrification |
Project Management of approx. 4000 stands
electrification |
|
10 |
Eskom Southern Region |
Tshabo & Siyathemba Village |
Electrification |
|
11 |
Eskom Southern Region |
Umtata Rural Phase 1 Electrification |
Electrification of approx 4574 connections.
|
|
12 |
Eskom Southern Region |
Zimbane-Ncora |
Building of 102km of 66kV Line |
|
13 |
Eskom Southern Region |
Zimbane SubStation |
66kV SubStation |
|
14 |
Eskom Northern Region |
Derdepoort/Batavia Line |
Audit and Refurbishment of 22KV line |
|
15 |
Eskom Northern Region |
Kareebos/Nantes/Pafuri 22KV lines |
Audit & Refurbishment of 22KV lines |
|
16 |
Eskom Northern Region |
RBA Extension |
Electrification of 1000 stands |
|
17 |
Eskom Northern Region |
Syferkuil-Dikgale 11KV line |
Refurbishment of SDA 11KV line |
|
18 |
Eskom Northern Region |
Spencer - Venulu |
132kV Feeder Bay & 50km Line + Bus Section Breaker |
|
19 |
Eskom Northern Region |
Witkop-Gompien |
Building of 42km of 132kV Line |
|
20 |
Eskom Eastern region |
Mlozana Electrification |
Electrification of Mlozana – Margate Area – 1200
stands |
|
21 |
Eskom Eastern Region |
Highflats NB 21 |
Refurbishment of Highflats NB21 22KV line |
|
22 |
Eskom Eastern Region |
Mtubatuba NB 07 |
Refurbishment of Mtuba 07 22KV line |
|
23 |
Eskom Eastern Region |
Gruneck NB03 |
Refurbishment of Gruneck 01 11 kV line |
|
24 |
Eskom Eastern Region |
Greytown NB01 |
Refurbishment of Greytown 11 kV line |
|
25 |
Eskom Eastern Region |
Wartburg NB22 |
Refurbishment of Wartburg-Wartburg Area |
|
26 |
Eskom Eastern Region |
Kwafodo |
Electrification of Kwafodo in Harding Area |
|
27 |
Eskom Eastern Region |
Dumezulu |
Electrification of Dumezulu in Port Edward
|
|
28 |
Eskom Eastern Region |
Ingwemabala |
Electrification of Ingwemabala-Port Edward Area |
|
29 |
Eskom Eastern Region |
Amacwera |
Electrification of Amacwera in Mount Frere Area |
|
30 |
Eskom Eastern Region |
Greenville |
Electrification of Greenville in Port Edward |
|
31 |
Eskom Eastern Region |
Phaphasi-Nhlwathi |
Electrification of 440 connections at Phaphasi |
|
32 |
Eskom Eastern Region |
Boswith |
Electrification of 300 connections at Boswith |
|
33 |
Eskom Eastern Region |
Kokstad NB2 |
Refurbishment of 11kV line |
|
34 |
Eskom Eastern Region |
Cedarville NB4 |
Refurbishment of 11kV line |
|
35 |
Eskom Eastern Region |
Franklin NB1 |
Refurbishment of 11kV line |
|
36 |
Bonesa – TSI Eskom |
Area and street Lighting-Pta/Brits/ Barberton |
Street t Lighting-Change to Energy Saving Type |
|
37 |
Buffalo City Municipality |
Lingelitsha |
Electrification of 457 stands |
|
38 |
Buffalo City Municipality |
Outspan Standby Generator Set |
Outspan /standby Genset |
|
39 |
Buffalo City Municipality |
Reeston Electrification |
Electrification of approx. +500 stands
including Streetlights |
|
40 |
Eastern Cape Public Works Department |
Tsolo Community Health Centres |
Building Electrical Services |
|
41 |
King William’s Town |
Phakamisa /Electrification |
MV and LV Reticulation for 1100 Stands |
|
42 |
Port Elizabeth Municipality |
Ibhayi Ext 3 Electrification |
MV and LV Reticulation for 450 Stands |
|
43 |
Nelson Mandela Metropolitan Municipality |
Bethelsdorp Electrification |
MV, LV Reticulation of approx. 214 stands in
Bethelsdorp Township |
|
44 |
Mhlontlo Local Municipality |
Electrification of Developer Project Areas |
MV and LV Reticulation of Qumbu & Tsolo Developer
Projects – Eskom Funded |
|
45 |
University of Fort Hare |
Facilities Management / Energy Management |
Complete Audit of Electrical Infrastructure |
|
46 |
Aliwal North Municipality |
Streetlight Project |
N6 and R508 Street lighting of approx. 2,5km each |
|
47 |
Kouga Municipality |
Greenfields Electrification |
Design & Project Management |
|
48 |
KSD Municipality |
Secondment of Responsible Person |
Heading the Electrical Directorate |
|
49 |
KSD Municipality |
Load Control and Energy Efficiency |
Implementing Demand Side Management measures for the
municipality |
|
50 |
Matjhabeng Municipality |
Pumpstation upgrade |
Project Management |
|
51 |
Matjhabeng Municipality |
Asset Valuation and Ringfencing |
Project Management |
|
52 |
Matjhabeng Municipality |
Load Control and Energy Efficiency |
Implementing Demand Side Management measures for the
municipality |
|
53 |
Swiftnet |
Business and Telecommunications Consultancy |
Process optimization and network upgrade and new
network installation. Design and project management |
|
54 |
Eskom Southern Region |
Zimbane S/S 2X10MVA |
Contract Project Management |
|
55 |
Eskom Southern Region |
Rhini Township Refurbishment |
MV, LV Reticulation |
|
56 |
Eskom Southern Region |
Refurbishment |
Kubusie Lines +/-600km |
|
57 |
Eskom Southern Region |
Developers
• Freestone
• Stationhill
• Loeriheuwel |
MV, LV Reticulation Total +/- 900stands |
|
58 |
Nelson Mandela Metropolitan Municipality |
Joe Slovo Electrification |
MV, LV Reticulation of 1600 erven |
|
59 |
Mbizana Municipality, DME Funded |
S/S Upgrade 2X15MVA |
Design, Tender, Construction Management |
|
60 |
KSD Municipality |
Umtata Rural Phase 1 |
4660 connections |
|
61 |
Eskom Southern Region |
Schools 2006/07 |
|
|
62 |
Eskom Southern Region |
Kubusi Lines |
Refurbishment |
|
63 |
City of Cape Town |
Load Control and Energy Efficiency |
Implementing Demand Side Management measures for the
municipality |
|
64 |
Eskom Northern Region |
Mashung electrification |
850 connections |
|
65 |
Eskom Northern Region |
Mantserre electrification |
150 connections |
|
66 |
Eskom Northern Region |
Pitsuilesdetang electrification |
85 connections |
|
67 |
Maluti-A-Phofung Municipality |
Load Control and Energy Efficiency |
Implementing Demand Side Management measures for the
municipality |
|
68 |
Spencer Venulu |
132kV 50km line |
Design, Tender, Construction Management |
|
69 |
Coleurs Generator Set |
50kVA Genset |
Design source and manage installation |
|
70 |
Fastnet Generator Set |
50kVA Genset |
Design source and manage installation |
|
71 |
JRA Generator Set and UPS |
JRA Backup Power |
Audit design and implement for 66 Sauer Street and 5
depots |
|
72 |
CRH-Conti International |
1150kVA Genset |
Install and commission |
|
73 |
Sony BMG |
185kVA Genset |
Proposal, design and install |
|
74 |
Coleurs |
Install 2 new lines |
Assess, design and implement new capacity |
|
75 |
Eskom Northern Region |
Goba Electrification |
300 connections |
|
76 |
Eskom Northern Region |
Phola |
100 Connections |
|
77 |
Eskom Northern Region |
Phomolong |
820 Connections |
|
78 |
Eskom Northern Region |
Masenya |
100 Connections |
|
79 |
Eskom Northern Region |
Mabusela ( Mapela ) |
100 Connections |
|
80 |
Eskom Northern Region |
Ga-Pila ( Stinkwater ) |
300 Connections |
|
81 |
Eskom Northern Region |
Dinisani-Mashathleng |
350 Connections |
|
82 |
Eskom Northern Region |
Taolome |
300 Connections |
|
83 |
Eskom Southern Region |
Khotana Phase 1 |
CPE and MV/LV survey services for 3838 connections |
|
84 |
Eskom Southern Region |
Ingquza Village |
CPE and MV/LV survey services for 2626 connections |
|
85 |
Eskom Southern Region |
Lady Frere 8B Phase 2 |
CPE and MV/LV survey services for 1767 connections |
|
86 |
Eskom Southern Region |
Lady Frere 8B Phase 3 |
CPE and MV/LV survey services for 1150 connections |
|
87 |
Eskom Southern Region |
Khanyayo Village Phase 1 |
CPE and MV/LV survey services for 2462 connections |
|
88 |
Centlec |
Energy Efficiency |
Implementation of Energy Efficiency Initiatives |
|
89 |
Eskom Southern Region |
Butterworth Phase 5 |
Turnkey Electrification 4000 Connections |
|
90 |
Eskom Southern Region |
Umtata Rural Phase 2 |
Turnkey Electrification 2914 Connections |
|
91 |
Eskom Southern Region |
Tsolo Phase 5B |
Turnkey Electrification 2900 Connections |
|
92 |
Eskom Southern Region |
Elliotdale Rural |
Turnkey Electrification 2300 Connections |
|
93 |
Eskom Eastern Region |
Malangeni Rural Ph 2 |
Electrification Project 1052 Connections |
|
94 |
Department of Works KZN |
King George V Hospital |
Electrical and Electronic Building Services |
|
95 |
Eskom Northern Region |
Kutlwanong ext Lovelife (2010/11) |
Electrification and design |
|
96 |
Eskom Eastern Region |
Schools |
2009 / 2010 Programme |
|
97 |
Centlec |
Energy Losses |
Investigation of technical and non-technical losses |
|
98 |
Maluti-A-Phofung Municipality |
Electrification Project |
1401 Connections |
|
99 |
Eskom Eastern region |
Franklin NB01 #1 |
Detailed Designs |
|
100 |
Eskom Eastern region |
Cederville NB04 #1 |
Detailed Designs |
|
101 |
Eskom Southern Region |
Schools and Clinics 2009/2010 |
Provision of CPE services 60 Schools |
|
102 |
Eskom Southern Region |
Schools and Clinics 2009/2010 |
Provision of CPE services 60 Schools |
|
|
|
|
|
|
103 |
Eskom Eastern region |
Perdekop |
Design of electrification for 32 connections |
|
104 |
Eskom Eastern region |
Msinga #1 |
Design of electrification for 1404 connections |
|
105 |
Eskom Eastern region |
eMabhanoyini |
Design of electrification for 600 connections |
|
106 |
Eskom Eastern region |
Khaleni & Zinini |
Design of electrification for 271 connections |
|
107 |
Eskom Eastern region |
Gwala & Mt Zion |
Design of electrification for 549 connections |
|
108 |
Eskom Eastern region |
Mkhandlwini (Bokplan) |
Design of electrification for 152 connections |
|
109 |
Eskom Eastern region |
Dumsi & Longweni |
Design of electrification for 1001 connections |
|
110 |
Eskom Eastern region |
Ndindindi #1 |
Project Management for the construction of 1105
connections |
|
111 |
Eskom North West |
Claystep 88kV Sub Refurbishment |
Project Management |
|
112 |
Eskom Eastern region |
Greytown 88kV Line |
Design and Project Management - Rebuild |
|
113 |
Eskom Eastern region |
Nagal Dam, New 132kV Substation |
Design and Project Management for the 22kV Turn in
Lines |
|
114 |
Eskom Eastern region |
Georgedale 88kV Sub-transmission Line |
Design and Project Management – Rebuild / Upgrade |
|
115 |
Department of Works KZN |
Stanger Hospital |
Electrical, Electronic, Mechanical Building Services |
|
116 |
Centlec |
Street Light Maintenance |
Upgrade and Maintenance of Street Lights |
|
117 |
Maluti-A-Phofung Municipality |
Electrification Project |
2000 Connections |
|
118 |
Centlec |
Solar Powered LED Street Light Installation |
Design and Project Management of LED Solar Powered
non-grid streetlight installation |
|
119 |
Eskom Eastern region |
Gowrie 132kV Sub-transmission Line |
Design and Project Management – Rebuild / Upgrade |